Key Achievements
Southern Cooper Basin Gas Project
- Klebb pilot upgrade – construction and commissioning successfully completed
- Klebb 3 - substantial increase in productivity
- Klebb 4 ESP performing well – step change in operating control
- Encouraging initial evaluation of shallow Epsilon coal
Strong Funding and Commercial Position
- Completion of $6.7 million capital raising
- Adelaide Brighton to join Strike’s gas customer group
- Cash on hand of $ 7.2 million at quarter end with funding in hand to advance the SCBGP project
Eastern Australian Gas Market
- Market prices move substantially higher
To view Report please download PDF attached: