Senex Energy Limited (Senex, ASX:SXY) is pleased to report that the Hornet-1 gas well is in pre-commissioning ahead of first gas sales for Senex.
Senex has completed a flow test of the Hornet-1 gas well during which gas flowed to surface at a rate of more than two million cubic feet per day. The well has been completed for production and the surface facilities, including the separation equipment and flowlines, have been installed. The pipeline connecting the Hornet field to the Santos-operated South Australian Cooper Basin Joint Venture (SACB JV) network at the Allambi field is ready for commissioning.