Pilot Plant concentrate leach feed started
-
Leaching of lepidolite concentrate has started with first feed reporting to the pilot plant on 25 June
-
Leach filter commissioned on slurry, operation scheduled to commence on 27 June for first production of amorphous silica
-
Production of first lithium sulphate intermediate scheduled for 1 July and SOP fertiliser on 7 July
-
Ramp-up to continuous operation of 15kg/hr target concentrate feed rate expected within two weeks
Lepidico Ltd (ASX:LPD) (“Lepidico” or “Company”) is pleased to announce that first concentrate reported into the Pilot Plant leach circuit on 25 June, marking the start of the ramp-up for the first operating campaign.