CuDeco advances towards Rocklands commissioning

Company News

CuDeco Limited (ASX:CDU) has mined 3,200 tonnes of native copper oar which it intends to stockpile for use in the commissioning of its Rocklands project in Queensland.

A minimum of 5 thousand tonnes of coarse Native Copper ore will be mined to be used for the commissioning.

Cudeco says significant quantities of ore have been diverted to high and low grade stockpiles, while additional ore will continue to be stockpiled.

The company will commence commissioning once it completes construction of its 500 tonnes per hour Primary and Secondary Crushing Circuits and tests them for one month.

CuDeco reported a $2.7 million loss in the first half of fiscal 2013. 