Empire Oil & Gas NL announces the total cost of the construction of the Red Gully Gas and Condensate Processing Facility including commissioning is AU$38.679 million.
Currently, the Red Gully Facility is producing natural gas at rates calculated at up to 8 terajoules a day and 500 barrels of condensate per day from the Gingin West-1 and Red Gully-1 wells. Condensate continues to be trucked to the BP Refinery, Kwinana.
During the two month Post Commissioning period as announced on 16 September 2013, there is provision for variable daily production rates when additional work is carried out to increase the efficiency of the Facility.