Media ReleasesAltech Chemicals

View All Altech Chemicals News


Altech Chemicals Announce HPA Plant Construction Update

ALTECH – HPA PLANT CONSTRUCTION UPDATE AUGUST 2019

Highlights

  • Majority of Stage 1 construction nearing completion
  • Workshop building now complete
  • OSD Tank walls finished and work underway on roof panel fabrication
  • Electrical substation design approved and earthworks to commence shortly
  • Stage 2 engineering activities have commenced
Altech Chemicals Limited (Altech/the Company) (ASX: ATC) (FRA: A3Y) is pleased to provide an update on the current status of construction activities at the Company’s high purity alumina (HPA) plant site in Johor, Malaysia.

For further information please download the attached PDF: Download this document