ALTECH – HPA PLANT STAGE 1 CONSTRUCTION UPDATE 

Highlights

  • Stage 1 construction progressing as planned
  • Site office, security post and safety systems established
  • Topsoil removed, bulk earthworks and levelling in progress
  • Piling rig mobilised to site
  • Steel for workshop procured and being sand blasted

Altech Chemicals Limited (Altech/the Company) (ASX: ATC) (FRA: A3Y) is pleased to provide an update of activities at the Company’s high purity alumina (HPA) project site in Johor, Malaysia, where Stage 1 construction is progressing as planned.