Silver Mines Announces Feasibility Study Completed - Bowdens Silver Project

Highlights

• Feasibility Study completed for a two million tonne per annum open-pit mining and conventional processing operation.

• Low strip ratio of 1.6:1.

• Production of 52.9 million ounces of silver plus 108.0 kilotonnes of zinc and 79.26 kilotonnes lead.

• Life of Mine (LOM) 16 years.

• Operating margin of A$558.70 million with project payback of 4.8 years.

• Initial three years of operations to produce concentrates containing 5.4 million ounces of silver per annum and 6000 tonnes of zinc and 5200 tonnes of lead per annum.

• LOM Operating C1 Cost of A$15.47/oz (US$11.60/oz) and an All in Sustaining Cost (AISC) of A$17.25 /oz (US$12.94/oz).

• Pre-tax Project NPV5 of A$143.90 million and IRR of 20.8%.

• Post-tax Project NPV5 of A$70.58 million and IRR of 17.9%.

• Sensitivity analysis demonstrates that the project is highly leveraged to an accretive commodity price environment.

• Initial development capital estimated at A$246 million.

• Board approval to complete remaining elements of the Environmental Impact Statement in lead up to Development Application submission.