Media ReleasesNSL Consolidated

View All NSL Consolidated News


NSL Consolidated Announces Phase Two Wet Plant - Major Commissioning Milestones Achieved

HIGHLIGHTS

- Phase Two wet beneficiation plant wet commissioning continues.

- Electrical commissioning of entire wet plant complete.

- Material fed into plant for first time with successful testing of materials handling systems.

- Wet plant electrically fully operational.

NSL Consolidated Limited (Company, ASX:NSL, NSLO), is pleased to update the market regarding the progress of its Phase Two Wet Beneficiation Plant.

Further to previous wet plant commissioning updates, a number of key milestones have been achieved during the past week. The electrical team have been able to fully complete all requirements associated with the electrical commissioning phase of the project, and therefore as a result the wet plant is electrically fully operational.


For further information please download PDF attached: 
Download this document

Subscribe to our Daily Newsletter?

Would you like to receive our daily news to your inbox?