Metro Mining Announces Bauxite Hills Mine Construction Update

Highlights

- Construction is on time and within budget

• Pile installation for marine infrastructure is complete
• Marine Offloading Facility is complete
• Civils for the Barge Loading Facility complete
• Haul road construction has begun
• 11 new camp buildings have arrived and are being installed

- Board & Xinfa Inspects Construction Progress

- Traditional Owners Join the Team

CONSTRUCTION OVERVIEW

The overall construction program at Metro’s Bauxite Hills Mine is advancing according to the schedule and is on budget.