Highlights

- Shipments in the September quarter were 822kt, with 2018 FY production and shipments guidance remaining unchanged.

- Refining results from bauxite processed in China highlight that Bauxite Hills material refines as anticipated.

Metro Mining Ltd (ASX:MMI) (Metro) is pleased to provide an update on its flagship Bauxite Hills Project.

In mid-September, Bauxite Hills shipped its one millionth tonne of ore since operations commenced in April 2018. This represents an excellent achievement for the project after just five months of operation, highlighting the strong commitment by Metro staff and contracting partners. By the end of September total shipments were 1.22 million WMT.