Metro Mining Announces Bauxite Hills Mine Commissioning

Highlights

- Critical infrastructure Barge Loading Facility successfully commissioned

- Haul road construction progressing well

- Camp, fuel farm and other infrastructure remains on track for completion by the end of 2017

- Project construction remains on budget and on track

CONSTRUCTION OVERVIEW

Marine Infrastructure

All major marine infrastructure has reached practical completion including the Barge Loading Facility (“BLF”), Marine Offloading Facility, cyclone moorings, navigational aids and tidal gauge. The BLF was recently wet commissioned with first product being loaded onto the conveyor system and into a barge.

The commissioning was a success with the BLF construction completed in only 5 months.