Highlights
- Construction is on time and within budget
• Pile installation for marine infrastructure is complete
• Marine Offloading Facility is complete
• Civils for the Barge Loading Facility complete
• Haul road construction has begun
• 11 new camp buildings have arrived and are being installed
- Board & Xinfa Inspects Construction Progress
- Traditional Owners Join the Team
CONSTRUCTION OVERVIEW
The overall construction program at Metro’s Bauxite Hills Mine is advancing according to the schedule and is on budget.