Grand Gulf Energy Limited (ASX: GGE) Dugas Leblanc no 3 Successful Casing

Napoleonville Dugas & Leblanc #3 Well, Assumption Parish, Louisiana, Non Operator 39.5% WI
 
The Dugas & Leblanc #3 well spudded on 16 April 2011 and reached TVD of 8,000ft (TD 8,920ft) on  Saturday, 30 April 2011. The well encountered gas shows through all primary intervals whilst drilling and a  further show was identified in a potential new "S" sand structure.
 
 The Board is pleased to advise that casing was successfully run to the bottom of the "S" sand at a TD of  8,503 ft. The casing was cemented and evaluation logs will be run in the next 24 hrs. A testing program is  due to commence within a week utilising a 24hr completion rig. Due to the proximity of the well to the  currently producing D&L#2, the well can be put on production in a very short period of time