SRH-1 (6H) WELL HAS GAS PIPELINE INSTALLED PLUS ADDING PERFORATIONS. EXPECTED TO GO ON PRODUCTION THIS WEEK. CONDENSATE RICH GAS SELLS FOR OVER US$7 PER MCF.
SRH-2 (8A) WELL UNLOADING FRAC FLUID. OIL HAS BROKEN THRU. CURRENTLY PRODUCING OIL AT A 109 BBL PER DAY RATE AND INCREASING. GAS PIPELINE BEING INSTALLED THIS WEEK.
SRH-3 (9M) WELL SUCCESSFULLY COMPLETED TO A DEPTH OF 9,454 FEET. CONDUCTING REMEDIAL CEMENT WORK IN PREPARATION FOR FRACTURE STIMULATION AT MONTH END (SOME DELAY IN FRACING DUE TO SEVERE WEATHER).
SRH-4 (9E) WELL HAS BEEN SUCCESSFULLY COMPLETED TO A DEPTH OF 9,454 FEET. A NEW BOTTOM HOLE INTERVAL (STRAWN) WILL BE TESTED IN THIS UP DIP WELL PRIOR TO FRACTURE STIMULATION.
SRH-5H WELL, OUR FIRST HORIZONTAL WELL IS COMPLETING PLANNING PHASE. LOCATIONS AND RIG HAVE BEEN IDENTIFIED. NEW “SLEEVE” FRACTURE STIMULATION PROGRAM BEING REVIEWED WITH HALLIBURTON. SPUD DATE EXPECTED LATE FEBRUARY.
Golden Gate Petroleum Ltd (ASX:GGP) is pleased to provide an update of operational activities in our Permian Basin Project located in Reagan County, Texas.